PPAP Level 3 for Custom LSR Parts: Submission and Approval Guide

Automotive and OEM buyers sourcing custom molded LSR seals, grommets, diaphragms or valves need evidence that a launch can repeat dimensionally, functionally and traceably. PPAP is not a trophy sample or a one-time FAI; it documents that the tool, process, measurement system and controls can produce conforming parts under defined conditions. For most programs, Level 3 is the working expectation: PSW, samples and complete supporting data. The goal is a package a customer can audit quickly, then release to stable production without surprises.

When PPAP Applies and Which Level to Request

Request PPAP when risk changes: a new part number, new cavity or tool, relocated production, revised material or process, engineering change, long shutdown restart, or a supplier/site transfer. LSR adds sensitivity because cure, flash, knit lines and deflection can drift even when a press looks stable. Ask early for customer-specific requirements, because they can override generic level logic.

LevelSubmissionTypical use
1PSW onlyLow-risk commodity parts
2PSW plus samples and limited dataReduced documentation cases
3PSW, samples and full supporting dataNormal automotive/OEM default
4Customer-defined elementsSpecial approvals only
5PSW, samples and complete data retained at supplierRare, audit-driven need

Treat the drawing revision, purchase order, quality agreement and CSR as one contract set. Level 3 is customary, but the signed CSR governs retention, format, software, boundary samples and whether run-at-rate evidence is separate.

Building the Process Evidence Package

Link flow, PFMEA and control plan by characteristic: a flow step creates a failure mode, the PFMEA assigns severity, occurrence and detection, and the control plan converts high-risk items into inspection, reaction and audit checks. A molder normally does not own DFMEA unless contractually design-responsible; otherwise design records are inputs, not owned deliverables.

GroupPPAP elements
Design and changeDesign records; engineering change documents; customer engineering approval if required; DFMEA only when design-responsible.
Process riskProcess flow diagram; PFMEA; control plan.
EvidenceMSA; dimensional results; material/performance results; initial process studies; qualified laboratory documentation.
Samples and toolsAppearance approval if applicable; sample parts; master sample; checking aids.
Customer closureCustomer-specific requirements; PSW.

Keep revision discipline tight: every ballooned print, cavity map, inspection sheet, material lot and tooling change must point back to the same engineering release. Missing this linkage is a common reason otherwise good LSR data receives conditional approval.

Measurement Systems and Process Capability

LSR parts are flexible, so measure with calibrated vision, CMM and constrained fixtures that represent functional fit. Typical LSR molding uses 140-180 °C mold temperature, 20-60 s cycles for small parts, and critical feature tolerances commonly near ±0.05 mm only when drawing-specific. Do not average away flash, short shots, contamination or tool wear.

CheckAcceptance guideAction
Gage R&R<10% generally acceptableUse with stable control plan
Gage R&R10-30% conditionalApply by characteristic risk and customer agreement
Gage R&R>30%Improve fixture, method, resolution or gage
Initial Ppk≥1.67 normal criterionSubmit with stable study
Initial Ppk1.33-1.67Customer agreement required
Initial Ppk<1.33Not acceptable without approved improvement plan

FAI proves selected articles meet the drawing at a point in time; PPAP proves the production system can repeat that conformity and remain controlled. Initial studies use Ppk from the significant production run, normally 1-8 hours and at least 300 consecutive parts unless the customer agrees otherwise. Ongoing Cpk is monitored later from production data. Thresholds above are acceptance criteria, not claimed results from a specific production run.

PSW Approval, Mass Production and Change Control

Approval does not waive incoming inspection, process audits or lot traceability. It means the buyer may start controlled production under the approved revision; it never permits silent changes to tool, cavity, process window, site or material.

PSW outcomeMeaningBuyer action
InterimShip allowed under containmentDefine expiry, traceability and exit criteria
FullSubmission accepted for the defined scopeRelease PO; maintain change control
RejectedEvidence incomplete or nonconformingStop shipment; correct root cause and resubmit
  1. RFQ: send drawings, tolerances, volume, CSR and annual capacity assumptions.
  2. DFM and quality planning: review parting lines, flash risk, inspection strategy and capability feasibility.
  3. Tool build and trials: document mold temperature, cycle time, cavity balance and samples.
  4. PPAP build: run the significant production run and capture dimensional, material and process evidence.
  5. Submit Level 3 or customer-defined package; resolve interim conditions.
  6. Approve PSW, complete run-at-rate if required, then launch controlled mass production.

Practical checklist: current ballooned drawing, approved flow/PFMEA/control plan, MSA for each gauge family, dimensional results by cavity, material and performance reports, process study assumptions, PSW, sample labels, master sample, checking aids and retention rules. Keep lot genealogy, tool history and revision linkage auditable through quality control and certifications.

Frequently Asked Questions

What PPAP level is required for custom LSR parts?

Level 3 is the normal full submission: PSW, samples and supporting data. Customer-specific requirements still govern level, format, retention and any additional run-at-rate evidence.

Is PPAP the same as first article inspection?

No. FAI verifies specific parts against the drawing at one point; PPAP proves the process can repeat conformity. PPAP adds flow, PFMEA, control plan, MSA, capability, samples and PSW.

How many parts are needed for a PPAP production run?

A significant production run is normally 1-8 hours and at least 300 consecutive parts, unless the customer agrees otherwise. The study should reflect intended tooling, operators, equipment and inspection methods.

Conclusion

A strong Level 3 package turns LSR complexity into repeatable evidence: stable tooling, linked flow-PFMEA-control plan, trustworthy measurement, honest capability criteria and disciplined change control. World Strong Rubber can review drawings and PPAP/customer-specific requirements for DFM and quality planning, supported by in-house mold making, ISO 9001/ISO 13485 systems and 28 years of manufacturing experience, without promising customer approval. Send your drawing revision, annual volume and CSR so the PPAP scope, gauge plan and launch evidence can be defined before steel is cut.

Related: equipment capacity · factory tour · mold making

✉️ Get a Quote 💬 WhatsApp 📞 +86 180 0288 9642
Chat on WhatsApp